Stocks in play: Continental Gold Inc.
Provided a construction update for its Buriticá project in northwestern Antioquia, Colombia. The project remains on schedule, with expected construction completion and first gold pour to take place in H1 2020. Commercial production ramp-up is still anticipated approximately six months after first gold pour. Overall construction is 44% complete with detail engineering more than 93% advanced. Underground development is 44% complete with 6,274 metres finished to date and continues to advance ahead of schedule. Process plant earthworks are 76% complete with mechanical installation scheduled to begin in early 2019. Continental Gold Inc. shares T.CNL are trading unchanged at $2.05.