Advertisement
Canada markets close in 45 minutes
  • S&P/TSX

    22,264.86
    +41.19 (+0.19%)
     
  • S&P 500

    5,537.02
    +28.01 (+0.51%)
     
  • DOW

    39,308.00
    -23.90 (-0.06%)
     
  • CAD/USD

    0.7347
    +0.0013 (+0.18%)
     
  • CRUDE OIL

    84.06
    +0.18 (+0.21%)
     
  • Bitcoin CAD

    79,319.52
    -2,527.20 (-3.09%)
     
  • CMC Crypto 200

    1,212.34
    -48.84 (-3.87%)
     
  • GOLD FUTURES

    2,369.40
    0.00 (0.00%)
     
  • RUSSELL 2000

    2,036.62
    +2.75 (+0.14%)
     
  • 10-Yr Bond

    4.3550
    0.0000 (0.00%)
     
  • NASDAQ

    18,188.30
    +159.54 (+0.88%)
     
  • VOLATILITY

    12.26
    +0.17 (+1.41%)
     
  • FTSE

    8,241.26
    +70.14 (+0.86%)
     
  • NIKKEI 225

    40,913.65
    +332.89 (+0.82%)
     
  • CAD/EUR

    0.6792
    -0.0003 (-0.04%)
     

Ontario Power Generation refurbishing eight hydroelectric stations for $1B

The Canadian Press

OTTAWA — Ontario Power Generation is spending $1 billion to refurbish eight hydroelectric generating stations in eastern Ontario.

Energy Minister Stephen Lecce says the project will extend the life of the stations for decades in order to help the province meet its growing electricity needs.

OPG is set to refurbish 45 units at the Arnprior, Barrett Chute, Mountain Chute, Stewartville, Chats Falls, Chenaux, Des Joachims, and Otto Holden stations, on the Madawaska and Ottawa rivers.

The work is also expected to allow the stations to produce 100 gigawatt hours of additional electricity each year, which is equivalent to powering more than 11,000 homes.

ADVERTISEMENT

OPG also recently announced a $600-million plan to refurbish a generating station in Cornwall.

The province says all of that hydroelectric refurbishment together will secure 1,617 megawatts of power, enough for 1.6 million homes.

This report by The Canadian Press was first published June 27, 2024.