Advertisement
Canada markets open in 2 hours 58 minutes
  • S&P/TSX

    22,011.72
    +139.76 (+0.64%)
     
  • S&P 500

    5,070.55
    +59.95 (+1.20%)
     
  • DOW

    38,503.69
    +263.71 (+0.69%)
     
  • CAD/USD

    0.7310
    -0.0010 (-0.14%)
     
  • CRUDE OIL

    82.98
    -0.38 (-0.46%)
     
  • Bitcoin CAD

    90,769.84
    +283.24 (+0.31%)
     
  • CMC Crypto 200

    1,431.48
    +7.38 (+0.52%)
     
  • GOLD FUTURES

    2,331.10
    -11.00 (-0.47%)
     
  • RUSSELL 2000

    2,002.64
    +35.17 (+1.79%)
     
  • 10-Yr Bond

    4.5980
    -0.0250 (-0.54%)
     
  • NASDAQ futures

    17,706.00
    +99.25 (+0.56%)
     
  • VOLATILITY

    15.83
    +0.14 (+0.89%)
     
  • FTSE

    8,090.24
    +45.43 (+0.56%)
     
  • NIKKEI 225

    38,460.08
    +907.92 (+2.42%)
     
  • CAD/EUR

    0.6836
    0.0000 (0.00%)
     

Paladin Energy Ltd: Thickener Failure Reduces Production for Approx 10 Days at Langer Heinrich

PERTH, WESTERN AUSTRALIA--(Marketwired - March 02, 2015) - Paladin Energy Ltd (PDN.TO) (PDN.TO) ("Paladin" or the "Company") wishes to advise that, the centrewell on pre-leach thickener #2 at Langer Heinrich failed, making this unit non-operational and necessitating its isolation from the process. Production now will rely on pre-leach thickener #1, reducing plant performance to around 45% of the production capacity.

Pre-leach thickener #2 is likely to be off-line for 8 to 12 days overall while necessary repairs are undertaken. On this estimate, the likely production loss is expected to be up to 100,000lb U3O8 for this quarter. This will likely impact stated production guidance and any revision of this will be advised once a clearer schedule for restart to full production is determined.